The contractors finished the exterior siding today.


The wood stove has been installed and is fully functional.

It’s still chilly though. The wall insulation is incomplete and the blow-in of roof insulation has been delayed until next Thursday.
The contractors finished the exterior siding today.


The wood stove has been installed and is fully functional.

It’s still chilly though. The wall insulation is incomplete and the blow-in of roof insulation has been delayed until next Thursday.
The siding on three walls are up. The contractors will be back on Friday to finish.

Shape of things to come.

Today was the first snowfall of the season. By early afternoon it had shifted to rain.

The contractor (Adam’s Yard Maintenance) had finished the house wrap and soffits by the end of last week. They will be back this week to start with the siding.

On the inside, I’ve been preparing the ceiling for the installation of blow-in insulation on November 24.
Scheduled for this week:
The windows and doors of the house are in!

I purchased a portable power station and charged it up with one of the solar panels today. It will be a source of power as I spend more time in the house. The solar power system will not be set up until I’ve prepared the ceiling for blow-in insulation contractor.
The building contractors return next week to install the soffits and hopefully get started with the siding, which was delivered today.