Today, the contractors built the back gabble end wall, applied the lower house wrap, and installed most of the windows & doors.

I shingled half the shed roof.

Today, the contractors built the back gabble end wall, applied the lower house wrap, and installed most of the windows & doors.

I shingled half the shed roof.

Another rainy day. The contractors haven’t been in this week.

I started preparing the underside of the roof for the blow-in insulation.
The shed was mostly closed in over the weekend.

Today I cleaned up the site.
Tomorrow, the contractor is back on site to start building the gable ends, finish the sheathing, apply the building wrap and install the windows & doors.
The contractors finished the roof by the end of last week. They will be back to close the gable ends and install windows & doors soon.

…and I’ve been building a shed.
The contractors arrived today. 🎉

The trusses were up by early afternoon.

Sheathing and fascia installation is underway.
Tomorrow they will start shingling.